· by Michael Blair, Nashville's Contractor
Anyone weighing a builder’s schedule for a custom house around Franklin or Nashville wants to know whether the months on paper are normal. The best public yardstick is the Census Bureau’s Survey of Construction, which records how long new single-family houses take from permit to start and from start to completion, by region and by who builds them. It has no Tennessee or Nashville figure, only the South as a whole, and it gives averages, not promises. Read for what it is, it still shows where a custom home sits against a house built for sale, and what to ask of any schedule.
How long does it take to build a house?
A new single-family house in the South took an average of 6.6 months from start to completion in 2025, according to the Census Bureau’s Survey of Construction tables on length of time. That figure covers every kind of house. Split by who builds it, the 2025 averages for the South were 5.5 months for houses built for sale, 9.0 months for houses built by a contractor on the owner’s land, and 10.8 months for houses the Census counts as owner-built. Nationally the same four figures were 7.4, 6.1, 10.5 and 12.8 months.
Two cautions come with those numbers. The South is a Census region covering many states, so none of them is a Tennessee or Nashville figure. And the survey records only the month a house starts and the month it is finished, so the Census counts a house started and completed in the same month as a full month. They are averages across a great many houses, a yardstick to hold a schedule against rather than a forecast for any one lot.
Is a custom home slower to build than a production home?
A custom home is slower to build than a production home in the Census figures, by roughly five to six months. Houses built for sale, the category that covers production and spec homes, averaged 5.5 months from start to completion in the South in 2025, against 10.8 months for owner-built houses, the Census column closest to a custom house built for the people who will live in it. The gap holds year to year: 5.7 against 11.7 months in 2024, and 6.8 against 11.6 in 2023.
The survey does not say why. What we see on our own builds is the point the custom homes page makes: a house with its selections made before the foundation is poured keeps to its schedule, and one where they are made as it goes does not. Each late decision tends to become a change, and our post on change orders covers how those add up in time and money.
How long between permit and groundbreaking?
Ground is broken about a month and a half after the permit is issued, on average. The Census Bureau’s authorization-to-start table puts the South’s 2025 average at 1.5 months, 1.6 for owner-built houses, and 1.4 nationally. Some jurisdictions let work begin before the final permit, so the Census notes the gap can be negative for some houses. The National Association of Home Builders’ September 2026 summary of the same data adds the two stages together, permit to completion, and puts the national average at 8.8 months, owner-built houses at 14.3, and the East South Central division, which includes Tennessee, at 9.1.
What comes before the permit is not in those numbers at all, and Metro does not publish a review time for it. Metro Codes’ residential building permits page gives no turnaround; it says the applicant is given a date for a permit application number. It does require a site plan for new construction and full construction plans for houses over 5,000 square feet. Our post on permits and inspections in Nashville covers how the process runs.
What should a builder’s schedule include?
A builder’s schedule should run from the permit to the day you can legally move in, with a date or a span for each stage in between, which is how we write ours. That means the expected permit date, groundbreaking, foundation, framing and dry-in, the rough-in inspections, finishes, and the final inspections. In Davidson County the end is the Use and Occupancy letter, covered in our post on the Use and Occupancy letter on a new house, not the last coat of paint.
It should also say what moves it. Weather is one, and our post on building through a Middle Tennessee winter covers what the cold changes. Selections due by a set date are another, so the schedule should list them. Hold the total against the Census averages for the South: a custom house quoted well under the contractor-built and owner-built figures deserves a question about what was left out. When you have a lot and a plan in mind, ask us for a schedule and an estimate.
Sources
- U.S. Census Bureau and HUD, Survey of Construction: Length of Time (tables revised April 29, 2026) — Average months from start to completion and from authorization to start for single-family houses, by region (South, a multi-state Census region, not Tennessee) and by built for sale, contractor-built and owner-built, 2023 to 2025; month-only recording; negative authorization-to-start
- National Association of Home Builders, Eye on Housing: Single-Family Home Construction Time Declines in 2025 (September 8, 2026) — A trade association’s summary of the Census data measured from permit to completion: 8.8 months nationally, 14.3 owner-built, about 11.7 contractor-built, 9.1 in the East South Central division
- Metro Nashville Codes, Residential Building Permits — No plan review time published; site plan required for new construction; construction plans required over 5,000 square feet
FAQ
How Long a House Takes to Build in the South — questions
How long does it take to build a house in Tennessee?
No Tennessee-only figure is published. The Census Bureau’s closest figure is for the South region: in 2025, an average of 6.6 months from start to completion for all new houses, 9.0 for contractor-built and 10.8 for owner-built. The NAHB puts the East South Central division, which includes Tennessee, at 9.1 months from permit to completion.
What is the average time to build a custom home?
The Census Bureau’s closest category is the owner-built house. In the South in 2025 it averaged 10.8 months from start to completion, and contractor-built houses on the owner’s land averaged 9.0. Nationally, owner-built houses averaged 12.8 months, and the NAHB puts them at 14.3 months once the wait between permit and start is added.
How long does a custom home take from permit to move-in?
Nationally, the NAHB’s reading of Census data puts owner-built houses at 14.3 months from permit to completion. In the South, permit to start averaged about 1.6 months for owner-built houses in 2025 and start to completion 10.8. In Davidson County, move-in also waits for Metro Codes’ Use and Occupancy letter.
Why do custom homes take longer than builder spec homes?
The Census figures show they do, 10.8 months against 5.5 in the South in 2025, but the survey does not record why. On our own builds, the schedule holds when the selections are made before the foundation is poured and slips when they are made as the house goes up, each late choice becoming a change.