· by Michael Blair, Nashville's Contractor
We build through the winter in Middle Tennessee, and most winter days allow it. The National Weather Service’s Nashville climate normals put the normal January high at 49.1°F and the low at 30.1°F, with about 19 January nights at or below freezing and 4.7 inches of snow in a normal year. The same table shows more than four inches of precipitation in each of December, January and February. So winter here means freezing nights and a lot of rain, and a schedule has to work around both.
Concrete, masonry, adhesives and paint each have limits in the cold, and the ground on a clay lot has limits of its own after a wet week. A homeowner who knows those limits can tell a prudent delay from one that is not.
Concrete and masonry
Freezing nights are the reason winter concrete takes planning here. We read the forecast for the days after a pour as closely as the day of it, and we hold a footing or a slab when a hard freeze is coming. When we do pour in a cold stretch, the fresh concrete goes under insulated blankets, and the mix is whatever the ready-mix plant recommends for that temperature. With a freezing night on about 19 January days by the Weather Service count, few winter weeks go by without one to plan around.
Mortar and grout are cement products as well, so they get the same caution. Our masons work to the cold-weather instructions for the mortar and grout they are using, cover fresh work before a cold night, and stop for the day when the forecast says the work cannot be protected.
Does rain or cold cost more winter building days?
Rain costs us more winter days on a Nashville lot than cold does. By the NWS normals, measurable precipitation falls on 11 or 12 days in each of December, January and February. We don’t dig footings or set a foundation in soaked clay, a footing trench that takes on water is pumped out before anything goes into it, and heavy equipment stays off a wet lot where we can keep it off, because it ruts the yard and the driveway.
Site work and foundations go on the calendar for a dry stretch, and the schedule has to be able to wait when the ground is wet. Grading and drainage are their own subject, covered on our hardscapes and site work page and in the post on when Metro wants a site grading plan.
Once the foundation is in and the house is dried in, the mud matters much less. Our framing crews work in the cold and stop for heavy rain and high wind. Soaked lumber is a separate concern: wood changes size as its moisture content changes, which is why the USDA Forest Products Laboratory’s Wood Handbook gives a whole chapter to drying, moisture content and dimensional change. A frame that got soaked is given time to dry before we close it up.
- Concrete and mortar: no pour with a hard freeze in the forecast, blankets in a cold snap
- Excavation and footings: a dry stretch, not a wet one
- Roofing: the shingle maker’s cold-weather instructions
- Paint, stain and adhesives: check each product’s minimum temperature
Can a roof go on in a Nashville winter?
Roofing goes on here all winter. The Weather Service puts Nashville’s average first freeze on November 11 and the average last one on March 31, and through those months our roofers work from the shingle manufacturer’s cold-weather installation instructions; where those call for sealing shingles by hand, the shingles are hand-sealed. On a cold morning they also take more care bending shingles into valleys and over ridges.
Siding, trim, caulk and exterior paint each come with the maker’s application temperatures, and our painters read them before a can is opened. A painter working an exterior in January is watching the overnight low as well as the afternoon high, since a 49°F afternoon here is normally followed by a night near 30°F. Vinyl siding is cut and hung to the manufacturer’s installation instructions, which we read against the temperature on the day it goes up.
What the schedule should look like
When we plan a winter build, the foundation goes into whatever dry weather the fall gives us; October is the driest month in the Nashville normals, at 3.36 inches. The aim is to have the structure dried in before the wet months and to run the interior trades through the winter, when the weather outside matters least. Until then, an open frame and the materials stacked beside it sit exposed to every winter storm, which is one more reason we settle who insures the house while it is being built before the foundation goes in.
We run temporary heat or start the permanent system early, so drywall, flooring, cabinets, tile and interior paint go into a heated house where each product’s temperature and humidity instructions can be met. Hardwood is delivered early and left in the heated house for as long as the flooring maker specifies before it goes down, since it moves with moisture like any other wood. That is the sequence we plan for a custom home that breaks ground in the fall.
What the homeowner should expect is a schedule with weather days built in, written product limits respected rather than argued with, and a contractor who says no to a pour or a paint day when the forecast is wrong. We would rather lose a few days than redo the work. If you are planning to build this winter, tell us about the project and we will walk through the calendar with you.
Sources
- National Weather Service Nashville, Nashville Climate Records — January normal high 49.1°F and low 30.1°F; 19 January days with a minimum at or below 32°F; 4.7 inches of snow a year; Dec, Jan, Feb precipitation over 4 inches with 11 to 12 days of measurable precipitation each; October normal 3.36 inches; average first freeze November 11 and last March 31
- USDA Forest Products Laboratory, Wood handbook: wood as an engineering material (FPL-GTR-282, 2021) — Chapters on moisture relations and on drying and control of moisture content and dimensional changes in wood
FAQ
Building Through a Middle Tennessee Winter — questions
Can you pour concrete in winter in Tennessee?
Yes, on most winter days, with planning. We check the forecast for the days after the pour, use the mix the ready-mix plant recommends for the temperature, cover fresh concrete with insulated blankets in a cold stretch, and hold the pour when a hard freeze is coming. Nashville’s normal January low is about 30°F, so freezing nights are routine all winter.
Is it cheaper to build in winter?
Not in any way we would promise. Weather days, temporary heat and cold-weather precautions for concrete all add cost, and they offset whatever scheduling ease the season brings. What winter is good for is the interior work, which carries on whatever the weather does outside.
Does winter rain delay construction more than cold?
In our experience, usually yes. Wet ground stops excavation, footings and any work that needs the soil to hold, and a clay lot can stay soft for days after the rain stops. Once the house is dried in, rain matters much less, and cold affects only the materials with temperature limits on their instructions.
Can you paint a house exterior in winter?
Often, within the limits printed on the product. Exterior paint, stain and caulk each carry the maker’s application temperatures, and in a Nashville January a 49°F afternoon is normally followed by a night near 30°F, so the overnight low counts as much as the daytime high. When the forecast misses the label, we move the paint day.