· by Michael Blair, Nashville's Contractor
When you build on your own lot, the last thing that happens is not the final walkthrough or the clean. In Davidson County it is a letter from Metro Codes saying the house can be used and occupied, and until it is issued the house is not finished on paper, however finished it looks. This is the end of building a custom home in Nashville: what Metro needs before it issues that letter, how the letter is requested, and what it means for planning the move. Cities outside Davidson County run their own offices, so this post stays with Metro.
When does a new house in Nashville get its use and occupancy letter?
At the very end, once every inspection on the permit has passed. Metro Codes’ page on applying for a Use and Occupancy letter says the letter is typically the last step in the building permit process. The list it depends on is set at the beginning: Metro’s building permit process page says an inspection checklist is issued with the building permit, naming the inspections needed to obtain the Use and Occupancy Certificate. That checklist is the job’s real finish line, and we work from it from the first day. The permits and inspections along the way are covered in our post on permits and inspections in Nashville.
Which code the house is inspected against depends on when it was submitted. Metro’s notice on adopting the 2024 International Building Codes says ordinance BL2025-898 was signed July 16, 2025, took effect on signature and applies to plans and applications submitted after that date, with a grace period for projects already designed under the 2018 codes.
What has to pass before Metro issues the letter?
Every building and trade inspection on the checklist. Metro’s permit process page says electrical, plumbing, gas/mechanical and low-voltage work each need their own permit and inspections, which a licensed subcontractor can pull once the building permit is issued, and that the final letter is requested from the Use and Occupancy Division after all building and trade inspections are done. The U&O page adds that the Building Final inspection should not happen until the trade permits are finished, and that the checklist can carry more inspections, which the inspector decides with the contractor.
In practice that sets the order at the end of a job:
- Trade finals: electrical, plumbing, gas/mechanical and low-voltage
- Any added inspections the inspector put on the checklist
- The Building Final
- The Use and Occupancy letter
How the letter is requested
Metro’s U&O page lays out the steps. Look the permit up in ePermits by its 10-digit number, open Available Reports and print the "CA Permit Status U&O REPORT", which shows whether every required inspection and permit is complete. Then request the letter by email, in person at the Building Inspection Division on the third floor of the Metro Office Building, or by phone at 615-862-6550; the page gives separate email links for residential and commercial requests.
We run that report ourselves before asking, so the request goes in once and is not bounced for an open trade permit. Metro says it wants to issue the letter as quickly as possible once a project is eligible. Its page lists no fee and no processing time, so we do not promise you a date for it either.
Can you move in before the final letter?
Plan as if you cannot. In the 2018 International Residential Code as published for Tennessee (the text we read on UpCodes), section R110.1 says a building may not be used or occupied until the building official has issued a certificate of occupancy. R110.4 lets the official issue a temporary certificate before all the work is complete, if the part to be occupied is safe, for a period the official sets.
That is the state-published model text. Metro Nashville writes its own administrative rules and issues its own Use and Occupancy letter, and the Metro pages we cite here do not describe a temporary letter for a house, so ask Metro Codes directly before counting on one. If the septic system on a lot without sewer is still being inspected, that has to close out too; see septic permits for a new home. When we build in Nashville, we set the closing, the lease end and the moving truck around the letter, not the last inspection date. If you are planning a house on your lot, talk to us about the schedule.
Sources
- Metro Nashville Codes, Apply for Use and Occupancy Letter — Typically the last step; trade permits before the Building Final; extra inspections set with the contractor; ePermits U&O report; email, in person (third floor, Metro Office Building) or 615-862-6550
- Metro Nashville Codes, Building Permit Process — Inspection checklist issued with the permit; separate trade permits pulled by licensed subcontractors; final letter from the Use and Occupancy Division
- Metro Nashville Codes, Metro adopts 2024 International Building Codes — BL2025-898 signed July 16, 2025, effective on signature, for submissions after that date; grace period for 2018-code designs
- 2018 International Residential Code as published for Tennessee, R110 (UpCodes) — R110.1 no use or occupancy before a certificate of occupancy; R110.4 temporary certificate
FAQ
The Use and Occupancy Letter on a New House in Nashville — questions
What is a use and occupancy letter in Nashville?
It is Metro Codes’ sign-off that a building permitted in Davidson County can be used and occupied. Metro calls it typically the last step in the building permit process. It is requested once every building and trade inspection on the permit’s checklist has passed, by email, by phone or in person.
Who issues the use and occupancy letter for a new house in Nashville?
Metro Nashville Codes. Requests go to the Building Inspection Division on the third floor of the Metro Office Building, by email or by phone at 615-862-6550. Before asking, print the CA Permit Status U&O report from the permit’s Available Reports in ePermits to confirm every inspection is complete.
What inspections come before a certificate of occupancy?
In Metro Nashville, every inspection on the checklist issued with the building permit. Electrical, plumbing, gas/mechanical and low-voltage work have their own permits and inspections, and Metro says the Building Final should not happen until those trade permits are finished. The inspector may add inspections to the checklist with the contractor.
Is a certificate of occupancy required for a new home in Tennessee?
The 2018 International Residential Code as published for Tennessee says, in R110.1, that a building may not be used or occupied until the building official issues a certificate of occupancy. Local governments run their own offices; in Davidson County the document is the Use and Occupancy letter from Metro Codes.
How do you get a temporary certificate of occupancy?
Under R110.4 of the 2018 International Residential Code as published for Tennessee, the building official may issue a temporary certificate before all work is complete if the occupied portion is safe, for a period the official sets. Metro Nashville’s pages do not describe its own terms for a house, so ask Metro Codes.